16/04/2015
The EIA decision D.M. 72 of 16 April 2015, amending the prescriptive framework (prescription A.13 is considered overcome) of the EIA Decision D.M. 223 of 9 September 2014 related to the project Trans Adriatic Pipeline - Albania-Italy pipeline, has been issued.
15/04/2015
The EIA-IPPC permit decision (D.M. 67 of 15 april 2015) related to the project "Drilling of new cultivation wells and adaptation of existing facilities to optimize the recovery of hydrocarbons from the offshore reservoir named Rospo Mare" has been issued with favourable outcome
15/04/2015
The EIA Follow-up determination - stage 1 (DVA-DEC-2015-0000090 of 15 April 2015) related to the project Completion the alternative gallery to gallery Pavoncelli of the aqueduct Sele-Calore, named Pavoncelli bis in the municipalities of Caposele and Conza (AV) has been issued with favourable outcome.
15/04/2015
The Project Change determination (DVA-DEC-2015-0000089 of 15 April 2015) related to Road link between Marche and Umbria and Quadrilatero di penetrazione. Maxi Lot 1. Sub lot 1.2. Change placement electrical substation CE05, has been issued with favourable outcome.
14/04/2015
The EIA compliance determination (DVA-DEC-2015-0000085 of 14 April 2015) on the prescription no.2 of the EIA Screening determination no. 688 of 10 January 2013 has been issued with favourable outcome.
03/04/2015
The EIA decision (D.M. 59 of 03/04/2015) related to the project "Geothermal Pilot Plant named Castel Giorgio in the Province of Terni, in the municipality of Castel Giorgio (TR)" has been issued with favourable outcome.
02/04/2015
The Project Change determination (DVA-DEC-2015-0000079 of 2 April 2015) related to the project Agrigento - Caltanissetta - A19 route, SS640 of Porto Empedocle - 2nd section from km 44 + 000 to the junction with the A19 - Variation plan construction site has been issued with favourable outcome.
02/04/2015
The EIA Compliance determination (DVADEC-2015-0000080 of 02/04/2015) on the prescription 10 of the EIA decision no.1264 of 31 October 2008 has been issued with favourable outcome.
31/03/2015
The EIA compliance determination (DVA-DEC-2015-0000070 of 31 March 2015) on the prescription no. 2 of the EIA decision no.3068 of 16 september 1998 has been issued with favourable outcome.
27/03/2015
The EIA Follow-up determination - stage 2(DVA-DEC-2015-0000065 of 27 March 2015) related to the environmental monitoring of the project A3 Salerno-Reggio Calabria motorway from km 411+400 to km 442+920 has been issued with favourable outcome.