Environmental Assessments and Authorizations: SEA - EIA - IPPC Permit
New 132 kV "Franchini acciai" electrical substation and 132 kV single circuit power line for the connection to the existing electrical substation of Brandico
Procedure Code (ID_VIP/ID_MATTM):
3702
Date of application submission:
05/09/2017
Data avvio consultazione pubblica:
08/09/2017
Deadline of submission of Public Comments:
23/10/2017
Technical assessment starting date:
13/09/2017
Date of request for integrations:
15/12/2017
Date of integrations receipt:
13/03/2018
Republication date of the notice:
30/03/2018
Deadline of submission of Public Comments on the republished project:
17/05/2018
Date of the Opinion of the National Technical Commission :
31/08/2018
National Technical Commission Opinion number:
2816
National Technical Commission Opinion outcome:
Escluso dalla VIA con prescrizioni
Determination date:
17/09/2018
Determination number:
DVA-DEC-2018-0000360
Determination outcome:
Escluso dalla VIA con prescrizioni
Notes:
Con nota del 29/01/2018 (prot. DVA-2018-0002174) è stata concessa una sospensione di 30 giorni del procedimento.